Sea Water Intake Pit – Basin 3 Liquid Bulk Terminal, Sokhna Port, (Sonker)

Project Information:
  • Type: Ports & Marines Infrastructure
  • Owner: Sonker Bunkering Company
  • Architect: ILF Consulting Engineers
  • Manager: Tebodin Middle East Ltd.
  • Contract Value: 19 Millions EGP
  • Status: Completed (2018)

Project Description:


  • The project consists of three stages :
    1. sea water intake pit
    2. sea water intake platform
    3. sea water outlet and diffuser
  • Construction of an intake pit which will be supplied by see water for petroleum firefighting purposes, temporary sheet piles installed for dewatering system